Night works at the Southbank Boulevard and City Road intersection are continuing until this Thursday night, 28 November, as previously advised.

Additional disruptive works are planned for December to finalise the installation of signal infrastructure and complete roadway asphalting works.

The works being carried out at night are only permitted by the Department of Transport to be undertaken between 8pm and 5am, in order to minimise traffic disruptions on City Road. The loudest works will be completed prior to midnight each night to reduce the impact on nearby residents.

Please see below for a program of works for the completion of the roadway prior to the end of 2019. These dates are dependent on the weather and ground conditions.

Regular updates will continue to be provided as works progress.

Please share this information with residents by placing this update in lifts and common areas where possible.

We appreciate your patience as we work towards completion of the roadway works for the Transforming Southbank Boulevard project.

Kind regards,

Southbank Boulevard Project Team